New Project- Replacement of an Air Handling Unit (AHU) at the embryological laboratory of New Life IVF, in Thessaloniki.
Project includes following works
- Dismantling of the existing unit
- AHU with direct expansion evaporator element (DX), resistors, filters, mixing box
- External Unit VRV
- Installation of a new unit on special levelling anti-vibration . Commissioning of the installation, operation setting, connection with sensors dP
- Supply and installation of new inlet, return and discharge channels adapted to the new AHU
- Electrical works of connection and power supply of the new AHU, cable routing rack and cooling pipes